“Update as of May 27, 2022”
The bridge closures are now halted until the next scheduled girder installation in August. NCDOT’s Barksdale stated, “We’ll repeat the same process and close this bridge twice a day for most of August to complete the girder installation. Those remaining girders will be placed on the north side and set into place by the same crane from the north bank of the river. This upcoming process in August will complete the girder installations.”
Members should know that the bridge on 701 over Cape Fear is scheduled to close for 1 hour between 9:00 and 10:00 am and 2:00 and 3:00 pm.
Road Work Days & Times
Weekdays 9am to 10am and 2pm to 3pm
Location:
• US-701 (Poplar Street), Near Broad Street
• In Elizabethtown / Both Directions
• Bladen County
Construction: Road Closed with Detour
Expect Bridge closures at Cape Fear River crossing weekdays from 9am to 10am and 2pm to 3pm in order to set girders of new bridge
Expected impact to traffic is High.
Detour
Signed Detour Route: NC 53 / SR 1318 (River Road) / SR 1316 (Tar Heel Ferry Road) / NC 87
Timeframe
Start back
August, 2022, 9:00 AM
End
”through most of August”
Road Work Days & Times
Weekdays 9am to 10am and 2pm to 3pm”